MYSORE : Project Cost
  Project Cost - Name of work : Construction of Truck Terminals at Junction of Mysore Nanjangud ring road
The costs for various items of work under phase 1 and its summary are as below:
Total summary of Cost - Phase 1
A brief on the proposed development area under Phase 1 as shown below:
Sl. No. Chapter No/Work Item Amount in Rs.
1. EARTHWORK SITE CLEARANCE AND DISMANTLING (for Entire area 16.20 acres) 7201233
2. STONE MASONARY WORK (for parks) 978877
3. DRAINAGE(For Entire Area) 15341222
4. RETAINING WALL (all around the area of 16.20 Acres) 8256924
5. FLEXIBLE PAVEMENT COURSES (Concrete Roads Phase 1 only) 17781915
6. RIGID PAVEMENT COURSES(Concrete Roads Phase 1 Only)  42814855
7. CULVERTS(Entire area) 8443903
8. TRAFFIC(Sign boards and Kerbs) 832376
9. UGD work(For Entire area) 1063683
10. STREET LIGHTS AND POWER SUPPLY(For entire area) 6861100
11. WATER SUPPLY (for entire area) 778882
12. DORMITORY for Cleaners and drivers(Gf +1st F + 2 F): Capacity of 50 beds in each floor 7200000
13. SULABH SOUCHALAYA + olice outot + Canteen 5000000
  Total Cost in Rupees 122554970
A Add Contigencies @ 2% 2451099
B Add Suervision charges for 18 months @ 3% 3676649
C. Add Escalation charges for 18 months @ 5.0% 6127748
  Total Cost for Phase 1 in rupees 134810466
  In crores 13.48
 
Total summary of Cost - Phase 2
Sl. No. Chapter No/Work Item Amount in Rs.
1. FLEXIBLE PAVEMENT COURSES (Idle Parking area) 10804516
2. RIGID PAVEMENT COURSES(Concrete Roads Phase 1 Only) 36316688
3. Agents Office + DDUTTL Admin Building 27500000
  Total Cost for Phase 2 in rupees 74621204
 
  Net Cost Estimate for Entire Area (Phase 1 + Phase 2) 197176173
A. Contigencies @ 2% 3943523
B. Suervision charges @ 3% 5915285
C. Escalation charges for 18 months @ 5.0% 9858809
  Total 216893790