MYSORE : Expenditure Details
  CONSTRUCTION OF PHASE -1 D. DEVRAJ URS TRUCK TERMINAL AT MYSORE RING ROAD-NANJANGUD JUNCTION
 
CONSTRUCTION OF PHASE -1 D. DEVRAJ URS TRUCK TERMINAL AT MYSORE RING ROAD-NANJANGUD JUNCTION
Sl No Work Item Contractor Amount in Rs. As Per BOQ Work Done UPTO RA BILL No-10 and Part in crores Under Progess Total Notes
1 EARTHWORK SITE CLEARENCE AND DISMANTLING 0.653     0.653 0.000 0.653 The quantity of the excavation and embarkment is achieved and both quantities are more than the Tendered Quantity. Actual Quantities of Embarkment is 92,500 cum and Excavation is 33.000 cum
a) Excavation  - 14672 CUM 14672 CUM
b) Embankment - 27347 CUM 27347 CUM
2 STONE MASONARY WORK 0.120 - - 0.083 0.005 0.088 Completed
3 DRAINAGE 1.452 2603 mtr 2490 mtr 1.3552 0.08 1.432 Completed
4 RETAINING WALL 0.980 1270 mtr 1130 mtr 0.970 0.100 1.070 Completed
5 FLEXIBLE AND RIGID PAVEMENT COURSES 5.960 - - 5.630 0.150 5.730 Completed
a) Roads   1050 mtr 1050
b) Idle Truck Parking   680 mtr 680 mtrs
6 CULVERTS 1.059 - - 0.560 0.150 0.710 Completed
7 TRAFFIC 0.123 - - 0.063 0.050 0.113 Completed
8 UGD WORK 0.117 - - 0.083 0.000 0.083 Completed
9 STREET LIGHTS AND POWER SUPPLY 0.732 - - 0.174 0.250 0.424 Cable laying work under progress.
10 WARE SUPPLY 0.083 - - 0.041 0.030 0.071 Completed
11 DORMITORY 0.833 - - 0.559 0.150 0.709 Sannitary & Electrical Fixature to be completed
12 SULABH SOUCHALYA 0.178 - - 0.095 0.060 0.155 Sannitary & Electrical Fixature to be completed
13 CANTEEN BUILDING 0.337 - - 0.228 0.050 0.278 Sannitary & Electrical Fixature to be completed
14 POLICE CHOWKI 0.041 - - 0.031 0.010 0.041 Paint & Electrical Fixature to be completed
(A) Total Amount 12.668     10.522 1.035 11.557  
  Additional Works and EFI              
1 EARTHWORK  0.980     1.100 0.010 1.110 Commercial area, park area and Plot area embarkment also Completed
a) Excavation  18328 cum 17037 cum
b) Embankment 68905 cum 57795 cum
2 11Kva UG Cable 0.121 - - 0.120   0.120 Completed
3 BUILDING Electrification 0.075 - -   0.040 0.040 Fixtures work under progess
4 Sign Board 0.055 - - 0.055 0.000 0.055 Completed
5 Land scappping 0.076 - - 0.035 0.035 0.070 Under completion
6 Power House 0.075 - -   0.050 0.050 Completed
7 Streetlights and Power Supply 0.340 - - 0.260 0.080 0.340 Cable laying work under completion.
8 Water, SupplySump & Drip 0.093 - - 0.068 0.020 0.088 Completed
9 Entreance Gate 0.037 - -   0.030 0.025 Under completion
(B) Total Amount 1.852     1.638 0.265 1.898  
Total of A + B in Rs 14.520     12.160 1.300 13.455